ICCGSA was awarded the bid for the execution of section Tacna – Collpa

  • This work of ICCGSA - Ingenieros Civiles y Contratistas Generales S.A will benefit more than 268 000 people.
  • The Project of 42 km in length will have an investment of S/. 141’413,510

Lima, February 04th, 2016.- The Ministry of Transport and Communications, through Provías Nacional, awarded the bid to ICCGSA of the road integration project of Tacna -  La Paz; section: Tacna – Collpa (The border with Bolivia), sub section: Km 146+180 (Dv.Tripartito) -Km 187 + 404. The project has a budget of S/. 141’413,510 (Peruvian currency)

This work consists on building 42 km of road at a hot asphalt layer. Also, it includes the construction of two bridges of 20 and 40 meters of length. The execution term is 540 calendar days.

This work will benefit directly more than 268 000 people of 15 districts which belong to Tacna, involving Tacna and Tarata and it will help to integrate the region economic and socially and improving the access of people to consumption centers. 